Question - Texas Transport Company supplies you with the following information about the two products they sell:

Tanker A Tanker B

Contribution margin per unit $4 $5

Materials per unit (pounds) 1 2

Direct labor hours per unit 4 2

There are 300 hours available in the plant and 100 pounds of materials available for production.

What is the objective function for maximizing profits?