The work on an it project is uniformly distributed over the


The work on an IT project is uniformly distributed over the project duration of 12 months. The total approved budget for the project is $720,000. At the end of the first quarter, 1/3rd of the project work is complete at a cost of $220,000. Determine the schedule variance, the cost performance index and the estimated cost at completion for the project.