The total cost of the current training is 80000 per year if


This is the confusing question. (and thanks for your help) A large research hospital is considering a new computer based training course for lad safety. The total cost of the current training is $80,000 per year. If new would reduce cost to $60,000, what is the maximum cost to initiate the program to reach the break-even point in 3 year? What is the ROI for that scenario? Any guidance would be appreciated.