The time study analyst ad dorben company developed the


The time study analyst ad Dorben company developed the following snapback stopwatch readings where element performance rating was used. The allowance for this element was assigned a value of 16 percent. What would be the standard time of this element?

Snapback reading Performance Factor

28 100
24 115
29 100
32 90
30 95
27 100
38 80
28 100
27 100
26 105

 