The time standard to make the valve shaft is 50 pieces per


The time standard to make the valve shaft is 50 pieces per hour. If the shop works at the rate of 80%, how many people would be required to cast 1,200 valve shafts per shift (8 hours)? If 50 minutes downtime is allowed per day, how many people are needed?

Case 1: without 50 minutes downtime:

(1) How many pieces do we need to make per shift?

(2) How many EFFECTIVE minutes does one shift have?

(3) Takt Time = Effective time during a period / Total quantity during a period

(4) How many pieces can be produced in one shift under effective time?

(5) How many people are needed = How many pieces do we need to make per shift / How many pieces can be produced in one shift under effective time.

Case 2: After 50 minutes downtime is considered:

How many EFFECTIVE minutes does one shift have?

Effective minutes = Nominal minutes – Downtime) × Efficiency