The time required for one team of employees to produce the


The time required for one team of employees to produce the first item is 100 hours. The learning curve percentage for unit number 70 is established to be 88%. At unit 71 the team of employees changes, while the time needed for the production of unit 71 increases by 10% when compared to the time needed for unit number 70. If the learning curve percentage for the new team of employees is 92%, what amount of time will they need to produce unit number 130?

Request for Solution File

Ask an Expert for Answer!!
Business Economics: The time required for one team of employees to produce the
Reference No:- TGS01630709

Expected delivery within 24 Hours