The table for this assignment provides best case most


MGT 251. Planning and Control

Project to Arrange for Conference

Questions:

  1. The table for this assignment provides best case, most typical case, and worse case estimates of task duration for each task. Using the PERT Beta distribution formulas, compute the expected time for achieving each task and its standard deviation.
  2. How long will the project take to carry out?
  3. What is the standard deviation of the critical path?
  4. What is project duration when 1s (standard deviation) is added? 2s? (Note that when dealing with normal distributions, about 68% of observations lie within ±1 s and about 95% of observations lie within ±2s. We do not have a normal distribution in this case. We are working with a PERT Beta distribution that is not fully symmetric. Still, using an assumption of normality, we can get a very rough sense of the probability that a project will slip its schedule by 1s or 2s.)
  5. Identify latest start, earliest start, and float times for each of the tasks in this project.

 

Expected duration

Latest Start

Earliest Start

Float

ID speaker topics

 

 

 

 

Contact speakers

 

 

 

 

Select hotel

 

 

 

 

Arrange hotel accommodations

 

 

 

 

Arrange catering

 

 

 

 

Develop brochure

 

 

 

 

Print and mail brochure

 

 

 

 

Develop exhibit material

 

 

 

 

Develop workbook

 

 

 

 

Print and bind workbook

 

 

 

 

Final set-up for conference

 

 

 