The standard direct labor time for producing one pair of


The standard direct labor time for producing one pair of original Crocs is 0.6 hours and the direct labor rate for producing one pair of original Crocs is $18.50 per hour. During February, 10,000 pairs of original Crocs were produced. Actual direct labor costs were $97,850 for 5,150 hours. Compute the direct labor rate variance and the direct labor efficiency variance for the month of February.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The standard direct labor time for producing one pair of
Reference No:- TGS01102342

Expected delivery within 24 Hours