The speed criterion has been assigned a weight of 04 and


In our decison matrix, Option 1 receives a "3" for speed and a "1" for cost, and option 2 received a "2" for speed and a "2" for cost. The speed criterion has been assigned a weight of 0.4 and the cost criterion has been assigned a whight of 0.6. In accordane with thedecision matrix approach, which of the following statement is true? 1) Option 1 is better thenOption 2 because its total weighted score is lower. 2) Option 1 and Opetion 2 each score a total of 1.8; therefore, either choice is fine. 3) Option 1 is better than Option 2 because its total weighted score is higher. 4) Option 2 is better thand Option 1 because its total weighted score is higher.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The speed criterion has been assigned a weight of 04 and
Reference No:- TGS02897705

Expected delivery within 24 Hours