The service times for a new data entry clerk have been measured and sequentially recorded as shown below:

Report

Time (Minutes)

1

66

2

56

3

53

4

48

5

47

6

45

7

44

8

41

a) What is the learning curve rate, based on this information?

b) Using an 85% learning curve rate and the above times, estimate the length of time the clerk will take to complete the 48th report.