The purpose of simulation project is to provide you with


Individual Project The purpose of this simulation project is to provide you with an opportunity to use the POM-QM for Windows software to solve an MRP problem.

POM-QM for Windows software For this part of the Individual Project, you need to use the POM-QM for Windows software:

1. Read Appendix IV of the Operations Management (Heizer & Render, 2011) textbook.

2. Launch the POM-QM for Windows software and from the main menu select Module, and then Materials Resource Planning.

3. Program the MRP for the Individual Project Problem below and solve it with the use of POM-QM for Windows.

Individual Project Problem The product structure tree for the finished product A is given below.

Product Structure Tree for Finished Product A The marketing department is estimating product A's demand to be 60 units for week 4 and 50 units for week 6.

There is a scheduled receipt of 75 units for component D at the beginning of week

2. Various other MRP related information for the finished products and the components are provided below.

A C D E On hand 12 170 9 5 Lead time 2 2 1 1 Lot size LFL 150+ multiples of 40 multiples of 22

Provide the MRP tables for all the finished products and the components for the next six weeks.

Solution Preview :

Prepared by a verified Expert
Management Information Sys: The purpose of simulation project is to provide you with
Reference No:- TGS0975324

Now Priced at $45 (50% Discount)

Recommended (92%)

Rated (4.4/5)