The project manager has just received a change from the


The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST?

A. Make the change happen as soon as possible

B. Contact the project sponsor for permission

C. Go to the change control board

D. Evaluate the impacts on other project constraints

Solution Preview :

Prepared by a verified Expert
Business Management: The project manager has just received a change from the
Reference No:- TGS01388887

Now Priced at $20 (50% Discount)

Recommended (95%)