The project is estimated to take 3 years and cost 9000000


Question - Construction Co. has a $11,400,000 contract to renovate the town's theater. The project is estimated to take 3 years and cost $9,000,000. End of first year, costs are $2,300,000. What is the percentage of completion at this point?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: The project is estimated to take 3 years and cost 9000000
Reference No:- TGS02761577

Now Priced at $20 (50% Discount)

Recommended (95%)