The predetermined factory overhead rate is 700 per direct


Question - At the end of April, Prichard Company had completed Jobs 50 and 51. Job 50 is for 200 units, and Job 51 is for 1,000 units.

The following data relate to these two jobs:

On April 20, raw materials were requisitioned for production as follows: 800 units for Job 50 at $22 per unit and 900 units for Job 51 at $14 per unit.

During April, Prichard Company accumulated 700 hours of direct labor costs on Job 50 and 1,200 hours on Job 51. The total direct labor was incurred at a rate of $20 per direct labor hour for Job 50 and $20 per direct labor hour for Job 51.

The predetermined factory overhead rate is $7.00 per direct labor hour.

a. Determine the balance on the job cost sheets for Jobs 50 and 51 at the end of April.

b. Determine the cost per unit for Jobs 50 and 51 at the end of April. Round all answers to the nearest whole cent.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: The predetermined factory overhead rate is 700 per direct
Reference No:- TGS02893084

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)