The plaintiff agrees to supply the defendants building


The plaintiff agrees to supply the defendant's building company with 2 tonnes of cement. During the negotiations the plaintiff agreed to supply at the price of $ 800 per tonne. The sales contract, prepared by the plaintiff, inadvertently states that the price is '$800' rather than '800 dollars per tonne'. When the plaintiff signs the contract he does not check that the price stated is per tonne. The defendant company seeks to defend a claim for payment of $ 1,600 on the grounds that the plaintiff is bound by the document signed to accept $ 800 for the cement.

Identify the nature of the mistake, and then determine if it is operative and state the consequences for the parties concerned.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The plaintiff agrees to supply the defendants building
Reference No:- TGS01530678

Expected delivery within 24 Hours