The performance rating was 95 percent and workday


A job was timed for 60 cycles and had an average of 1.3 minutes per piece. The performance rating was 95 percent, and workday allowances are 17 percent. Determine each of the following:

a.Observed time. (Round your answer to 1 decimal place.)

Observed time minutes 

b.Normal time. (Round your answer to 2 decimal places.)

Normal time minutes 

c.Standard time. (Round your answer to 2 decimal places.)

Standard time minutes