The performance rating was 93 percent and workday


A job was timed for 60 cycles and had an average of 2.3 minutes per piece. The performance rating was 93 percent, and workday allowances are 14 percent. Determine each of the following:

Observed time. (Round your answer to 1 decimal place.)

Normal time. (Round your answer to 2 decimal places.)

Standard time. (Round your answer to 2 decimal places.)

Solution Preview :

Prepared by a verified Expert
Business Management: The performance rating was 93 percent and workday
Reference No:- TGS02437901

Now Priced at $10 (50% Discount)

Recommended (99%)

Rated (4.3/5)