The percentage utilization for the sequence developed using


The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 (day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.

Job Date Job Received Due Date Duration (days)

BR-02 225 270 25

CX-01 230 320 35

DE-06 235 360 40

RG-05 231 310 30

SY-11 228 300 15

Using the FCFS? (first come, first? served) decision rule for sequencing the? jobs, the order? is:

The average tardiness? (job lateness) for the sequence developed using the FCFS rule? =

The percentage utilization for the sequence developed using the FCFS rule?

The average completion time for the sequence developed using the FCFS rule?

The average number of jobs in the system for the sequence developed using the FCFS rule? =