The overall average on a process you are attempting to


The overall average on a process you are attempting to monitor is 50 units. The average range is 4 units. The sample size is 5. What are the upper and lower control limits of a 3 sigma mean chart?

A. Upper control limit is 52.31 and the lower is 47.69.

B. What are the upper and lower control limits of 3 sigma range chart??