The manager finds that there are 100 applications in the


The manager finds that there are 100 applications in the system. Based on the last week’s performance, his staff can process 1000 applications in a week (assume one week has 5 days and one day has 8 hours). Suppose it takes 10 minutes to process one application. What is the cycle time, throughput and throughput efficiency?