Sonya marx operates a machine 340 minuted a day. the actual cycle time per part on the machine is measured to be 0.8 minutes and the machine produces 360 parts a day. The machine specifications indicate that it should have a cylce time of 0.75 min/part. what is the performance  efficiency of the machine ?

Sonya's machine descirbed in problem 6 is scheduled to operate 390 minutes a day. About six parts per day from the machine are rejected as nonconforming.what is the machines OEE?