The line will operate for 480 minutes per day awhat are the


An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest takes .3 minutes. The line will operate for 480 minutes per day. a. What are the maximum and minimum cycle times? b. What output rate will be achieved by each of those cycle times?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The line will operate for 480 minutes per day awhat are the
Reference No:- TGS0562551

Expected delivery within 24 Hours