The length of time x to complete a certain key task in


The length of time X to complete a certain key task in house construction is exponentially distributed random variable with a mean of 10 hours. The cost C of completing this task is related to square of the time to completion by the formula

C = 100 + 40X + 3X2

a Find the expected value and variance of C.

b Would you expect C to exceed 2,000 very often?