Question - Brown Laundry has a variable demand. The daily demand ranges from 100 to 140 customers a day with an average of 5 items. The average daily demand is 110 customers. The laundry operates 10 hours a day. Each order takes approximately 5 minutes.

Required: What is the average customer waiting time, in minutes?