The injector machine goes down roughly 20 of the time what


The injector machine goes down roughly 20% of the time (the injector gums up and needs to be cleaned, a quick process). One operator is assigned to service three identical such machines. Each machine can produce 100 parts/hr if running properly (i.e. not down). The operator is paid $10.00/hr and each machine costs $20.00/hr to operate. What is the unit cost for this operation?