The injection moulding department of a company that operates 24x7 uses an average of 20 gallons of special lubricant per day. It takes two weeks for an order of lubricant to be delivered.

a. If safety stock is enough for two days, what is the reorder point?

b. If the usage of lubricant is normally distributed, with a standard deviation of 5 gallons per day and the company wants a service level of 87%, what is the reorder point?