The initial outlay or cost for a four-year project is


The initial outlay or cost for a four-year project is $1,000,000. The respective cash inflows for years 1, 2, 3 and 4 are: $500,000, $300,000, $300,000 and $300,000. What is the discounted payback period if the discount rate is 10%?