The following timephasing chart is available for a single


The following timephasing chart is available for a single item within a MRP system. 

Complete this chart by estimating inventory on hand and planned order release values. 

Lead time is 2 weeks and order policy is 100 units, which means this part can be ordered only in 100unit batches. Inventory replenishment is JIT, lead times are negligible. 

Week Number

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

80

95

 

110

 

 

50

 

Scheduled Receipt

100

 

 

 

 

 

 

 

 

 

Inventory on Hand

 

 

 

 

 

 

 

 

 

 

Planned Order Release

 

 

 

 

 

 

 

 

 

 

 

 

 