The following table shows the activity details of a project


The following table shows the activity details of a project. What the earliest the project can be completed?

Activity Days Predecessor ctivities

 

A 4 -

B 5 -

C 3 A

D 5 A

E 7 B

F 2 D,E

G 6 C,F

 