the following represents a project that should be


The following represents a project that should be scheduled using CPM:

Time (DAYS)

Activity Immediate Predecessors a m b
A - 1 3 5
B - 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C, D 3 4 5
G D, E 1 4 6
H F, G 2 4 5

a. Draw the network

b. What is the critical path?

c. what is the expected project completion time?

d. What is the probability of completing this project within 16days?

Any and all help will be quite helpful

Request for Solution File

Ask an Expert for Answer!!
Operation Management: the following represents a project that should be
Reference No:- TGS0402267

Expected delivery within 24 Hours