The following jobs must be processed in the super clean


The following jobs must be processed in the Super Clean motor shop. Assume that the company operates seven days per week. Today is November 10. Using FCFS, SPT, and EDD as the priority rules, calculate average job tardiness, average flow time, and the number of tardy jobs

Job             Arrival Date                   Work Required (in Days)                              Due Date

A                Nov. 1                                            8                                         Nov. 16

B                Nov. 4                                            1                                         Nov. 11

C                Nov. 2                                            20                                         Nov. 21

D                Nov. 3                                            5                                         Nov. 13

E                 Nov. 6                                            3                                         Dec 2

F                 Nov. 5                                            4                                         Dec 10