The following jobs are waiting to be processed at rick


The following jobs are waiting to be processed at Rick Solans machine center. Solans machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day) compute all times based on initiating work on day 241.

Job Date job recieved due date duration (days)

BR-02 225 270 25

CX-01 230 320 35

DE-06 235 360 40

RG-05 232 310 30

SY-11 228 300 15

Using the FCFS decision rule for sequencing the jobs, the order is? (1,2,3,4,5)

The total flow time for the sequencing developed usint the FCFS rule? (round response to two decimal places)

The percentage utilization for the sequence developed using the FCFS rule? (rounded to two decimal places)

the average number of jobs in the system for the sequence developed using the FCFS rule? (rounded to two decimal places)

The average tardiness for the sequence developed using the FCFS rule? (rounded to two decimal places)

Using the EDD decision rule for sequencing the jobs, the order is? (1,2,3,4,5)

The total flow time for the sequencing developed usint the EDD rule? (round response to two decimal places)

The percentage utilization for the sequence developed using the EDD rule? (rounded to two decimal places)

the average number of jobs in the system for the sequence developed using the EDD rule? (rounded to two decimal places)

The average tardiness for the sequence developed using the EDD rule? (rounded to two decimal places)

Using the SPT decision rule for sequencing the jobs, the order is? (1,2,3,4,5)

The total flow time for the sequencing developed usint the SPT rule? (round response to two decimal places)

The percentage utilization for the sequence developed using the SPT rule? (rounded to two decimal places)

the average number of jobs in the system for the sequence developed using the SPT rule? (rounded to two decimal places)

The average tardiness for the sequence developed using the SPT rule? (rounded to two decimal places)

Using the LPT decision rule for sequencing the jobs, the order is? (1,2,3,4,5)

The total flow time for the sequencing developed usint the LPT rule? (round response to two decimal places)

The percentage utilization for the sequence developed using the LPT rule? (rounded to two decimal places)

the average number of jobs in the system for the sequence developed using the LPT rule? (rounded to two decimal places)

The average tardiness for the sequence developed using the LPT rule? (rounded to two decimal places)