The following is a table of activities associated with a


The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, and what activities each must precede:

Activity

Duration (weeks)

Precedes

A (start)

1

B, C

B

1

E

C

4

F

D

2

F

E (end)

2

-

a) Draw an AON diagram of the project, including activity durations.

b) Define the critical path, listing all critical activities in chronological order.

c) What is the project duration (in weeks)?

d) What is the slack (in weeks) associated with any and all noncritical paths through the project?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The following is a table of activities associated with a
Reference No:- TGS02156897

Expected delivery within 24 Hours