The following is a table of activities associated with a


The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:

Activity Duration (weeks) Precedes

A (start) 1 B, C

B 1 E

C 4 F

E 2 F

F (end) 2 _

a) Draw an AON diagram of the project including activity durations

b) Define the critical path, listing all critical activities in chronological order and list the project duration (in weeks)?

c) What is the project duration in weeks?

d) What is the slack in weeks with any and all noncritical paths through the project?