The following information relates to bs ordering activity


Simple ABC overhead variance  analysis

The following information relates to B's ordering activity during control period 2.

Budget

Output                       10,000 units

Activity level                2,000 orders Total cost of activity               $90,000

Actual

Output                       10,500 units

Activity level                1,800 orders Total cost of activity               $84,000

Required

Calculate the overhead expenditure and efficiency variances relating to the ordering activity.