The following information is given for a particular part


Question: 1. The following information is given for a particular part. Using a lead time of two weeks, complete the table. Use L4L with On hand = 80 and SS=0.

2490_Gross.png

2. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows:

227_Gross 1.png

The firm would like to produce 600 chairs in week 5 and 300 chairs in week 6.

a. Develop a materials plan for all the parts.

b. What actions should be taken now?