The following data were obtained from a project to create a


Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity           Duration         Predecessors 

A                     5 Days             ---

B                     6 Days             ---

C                     8 Days             ---

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity D?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity H?

g) What is the float for Activity I?

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity           Duration         Predecessors 

A                     6 weeks           ---                               

B                     6 weeks           ---                               

C                     5 weeks           B                                

D                     4 weeks           A, C                           

E                      5 weeks           B                                

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week             I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 3

The following data were obtained from a project to design a new software package:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     6 Days             A                                

D                     4 Days             C, B                            

E                      5 Days             A                                

F                      4 Days             D, E, G                                   

G                     4 Days             B, C

H                     3 Day              G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 4

The following data were obtained from an in-house MIS project:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     5 Days             A                                

D                     4 Days             B

E                      5 Days             B                                

F                      3 Day              C, D               

G                     7 Days             C, D

H                     6 Days             E, F, G

I                       9 Days             E, F

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?