The following data is received from your contractor on a


The following data is received from your contractor on a project's key component: Budgeted Cost of Work Performed (BCWP) = $100 Budgeted Cost of Work Scheduled (BCWS) = $200 Actual Cost of Work Performed (ACWP) = $100 Budget at Completion (BAC) = $500 Latest Revised Estimate (LRE) = $900 Which of the following Earned Value Management (EVM) metrics can be determined from these data:

SPI = 2.0, CPI = 1.0, TCPI(BAC) = 1.0, TCPI(LRE) = 1.0

SPI = 0.5, CPI = 1.0, TCPI(BAC) = 2.0, TCPI(LRE) = 0.5

SPI = 0.5, CPI = 1.0, TCPI(BAC) = 1.0, TCPI(LRE) = 0.5

Schedule Performance Index (SPI) = 2.0, Cost Performance Index (CPI) = 1.0, To-Complete Performance Index [TCPI](BAC) = 2.0, TCPI(LRE) = 1.0.