The following data is given for the stringer company-


The following data is given for the stringer Company:

Budgeted production1,044

unitsActual production 925

unitsMaterials:

Standard price per ounce$1.78

Standard pounds per completed unit10

Actual pounds purchased and used in production8,973

Actual cost of materials$18,395

Labor:

Standard hourly labor rate$15.00 per hour

Standard hours allowed per completed unit4.0

Actual labor hours worked4,763.75

Actual total labor costs$72,647

Overhead:

Actual and budgeted fixed overhead$1,081,997

Standard variable overhead rate$28.00 per standard labor hour

Actual variable overhead costs$133,385

Overhead is applied on standard labor hours. Determine the direct material quantity variance.

Solution Preview :

Prepared by a verified Expert
Financial Accounting: The following data is given for the stringer company-
Reference No:- TGS01540029

Now Priced at $5 (50% Discount)

Recommended (97%)

Rated (4.9/5)