The expected demand in october is 20000 units and there are


The expected demand in October is 20,000 units, and there are 25 working days in October. The production rate is 10 units per day per employee. The initial inventory is 1,000 units, and the ending inventory target is 5,000 units. Following a chase strategy, how many employees would be needed in October?

A. 16

B. 54

C. 96

D. 108