The discount rate the firm wants to use for the project is


GDebi Enterprises is thinking of building a chemical processing plant to produce 4-hydroxy-3-methoxybenzaldehyde. The firm estimates that the initial cost of the project will be $12.1 million, and the plant will produce cash inflows of $6.9 million for the next 5 years, after which time the project will terminate. In the 6th year however, the firm will need to clean up the site, which it estimates will cost it $3 million. The discount rate the firm wants to use for the project is 14.9 percent. What is the NPV of this project? (Enter answer in millions.)

Request for Solution File

Ask an Expert for Answer!!
Financial Management: The discount rate the firm wants to use for the project is
Reference No:- TGS02844063

Expected delivery within 24 Hours