The decision criterion in the net present value approach to


The decision criterion in the net present value approach to capital budgeting is to accept the project if ______, and otherwise to reject the project.

a) NPV is equal to zero

b) NPv is less tha zero

c) NPV is greater than zero

d) NPV is greater than or equal to zero