The critical path on a particular project consists of 10


The critical path on a particular project consists of 10 activities and the expected completion time on those 10 activities is 45 days. If the total variance on the critical path for all 10 activities together is 6 days, what is the chance that you will be able to complete the project within 55 days? If your client provides you with a target completion date of 44 days, would you take it up? Give your reasoning for the answer and explain/show the calculations.