The cpm critical path method is a method to identify the


The CPM (Critical Path Method) is a method to identify the critical path, which:

A-consists of all the activities in which the Project Manager is involved.

B-is composed of all non-dummy activities in the project.

C-is made of the shortest path connecting the beginning to the end of the project.

D-is made of the longest path connecting the beginning to the end of the project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The cpm critical path method is a method to identify the
Reference No:- TGS01273288

Expected delivery within 24 Hours