The company now wants to build a new facility on that site


Kelly's Corner Bakery purchased a lot in Oil City six years ago at a cost of $278,000. Today, that lot has a market value of $264,000. At the time of the purchase, the company spent $6,000 to level the lot and another $8,000 to install storm drains. The company now wants to build a new facility on that site. The building cost is estimated at $1.03 million. What amount should be used as the initial cash flow for this project

-$1,294,000
-$1,308,000
-$1,308,000
-$1,322,000
-$1,045,000