The company has just received a contract calling for


Stanley Electronics Products, Inc., finds that new-product production is affected by an 80 percent learning effect. The company has just produced SO units of output at 100 hours per unit. Costs were as follows:

Materials @ $20

$1,000

Labor and labor-related costs:


Direct labor-100 hours @ $8

800

Variable overhead-100 hours 0 $2

200


$2,000

The company has just received a contract calling for another SO units of production. It wants to add a 50 percent markup to the cost of materials and labor and labor-related costs. Determine the price for this job.

 