The company has budgeted for 6350 hours of technician time


Ignatenko's Custom Electronics (ICE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available.

 

 

Time Charges

 

Material Loading Charges

 

Technicians' wages and benefits

$165,100

   

-       

   
 

Parts manager's salary and benefits

-       

   

$33,580

   
 

Office employee's salary and benefits

29,083

   

9,328

   
 

Other overhead

14,351

   

41,888

   
 

Total budgeted costs

$208,534

   

$84,796

 

The company has budgeted for 6,350 hours of technician time during the coming year. It desires a $37.72 profit margin per hour of labor and a 100% profit on parts. It estimates the total invoice cost of parts and materials in 2014 will be $680,000.

Compute the rate charged per hour of labor. 

Labor rate

 

$https://edugen.wileyplus.com/edugen/art2/common/pixel.gif

per hour

Compute the material loading percentage.

Material loading percentage

 

https://edugen.wileyplus.com/edugen/art2/common/pixel.gif

%

       

 ICE has just received a request for a bid from Buil Builders on a $1,205,000 new home. The company estimates that it would require 81 hours of labor and $38,000 of parts. Compute the total estimated bill. 

Total estimated bill

 

$https://edugen.wileyplus.com/edugen/art2/common/pixel.gif

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: The company has budgeted for 6350 hours of technician time
Reference No:- TGS01211840

Expected delivery within 24 Hours