The city of morse recently completed the construction of a


The city of Morse recently completed the construction of a bridge across the Ohio River at a total cost of $133,453.95. The length of the bridge is 276,389 feet. The city of Edison three miles up river wants to build there own bridge which have to be 124,866 feet in length. Estimate Edison's cost of construction assuming power sizing constant for this type of construction is 0.56