The chattanooga furniture store gets an average of 50


The Chattanooga Furniture store gets an average of 50 customers per shift. Marilyn Helms, the manager, wants to calculate whether she should hire 1, 2, 3, or 4 salespeople. She has determined that average waiting times will be 7 minutes with one salesperson, 4 minutes with two salespeople, 3 minutes with three salespeople, and 2 minutes with four salespeople.

She has estimated the cost per minute that customers wait at $1. The cost per salesperson per shift (including fringe benefits) is $70. How many salespeople should be hired?