The chart below shows the master production schedule mps


The chart below shows the Master Production Schedule (MPS) and committed customer orders for a new MP3 Player you manufacture. Based on this information calculate Available to Promise (ATP.) Discrete ATP Calculation MP3 Player Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 MPS BI=25 250 300 350 300 300 250 200 100 Committed Customer Orders 200 350 350 325 250 275 175 110 ATP:D